The Town of Nantucket is planning to replace the existing 1960’s Harbormaster building with a new facility at its current location at 34 Washington Street adjacent to the Town Pier, which is also undergoing much needed renovations. An appropriation of $3,450,000 was approved in Article 17 of the Town’s 2018 Annual Town Meeting for the project.  

The Town received a grant award of $1,000,000 from the Massachusetts Seaport Economic Council for this project in August 2018.  Coastal Engineering Company won a competitive bid for the project and is working with Stephen Kelleher Architects to design a 3,400-square-foot, two-story structure that meets the historic district as well as a FEMA velocity zone require­ments.

image004
image002

Project Budget:

Project is subject to MGL c.149 and MGL c. 30B

Total Appropriation: $3,450,000.00

  •  Architectural, Engineering & Design Fees (total $189,500 as follows)
    •  Schematic Design- Complete
    • Design Development- $40,000
    • Construction Documents- $80,000
    • Bidding- $7,000
    • Construction Administration $60,000
    • Project Closeout- $2,500
  • Construction Fees
    • Building Construction $2,500,000
    • Site Work- $500,000
  • Furniture, Fixtures & Equipment- $260,500

Project Timeline (prior to disruption due to COVID-19*):

  • Nov 2018 – Design, engineering, survey complete
  • Dec, 2018 – Bid Advertised
  • Jan, 2019 – Bid opening
  • Jan, 2019 – Award contract
  • Feb, 2019 – Construction start date
  • Apr, 2019 – 25% complete
  • Jun, 2019 – 50% complete
  • Aug, 2019 – 75% complete
  • Oct, 2019 – 100% complete
  • Dec, 2019 – Contract Expiration Date

*Revised timeline pending